|
|
|
|
|
|
|
|
|
|
|
|
The Belmont Viaduct
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Grenada Village is the site of one of the
great engineering achievements of 19th century New Zealand. Seton Nossiter Park
contains the remains of the famous Belmont Viaduct that traversed the steep gully
beside Mark Avenue. The viaduct was a memorable and distinctive part of this country's
early transport system.
|
|
|
|
|
|
|
|
|
The Belmont Viaduct
|
|
|
|
|
|
|
|
|
|
Photo: Alexander Turnbull Library
|
|
|
|
|
|
|
|
|
|
|
|
The original gigantic wooden span played an
important role in developing early Wellington, as not only did it open up the city's
northern boundaries, it also provided access to the 'hinterlands' of Horowhenua
and Manawatu.
The viaduct was constructed for the privately
owned Wellington & Manawatu Railway Company in 1885 and was the largest wooden structure
of its kind in New Zealand. It was at the time reputed to also be the largest wooden
viaduct in the world, however this was later disproved as some spans in Canada were
bigger.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Its construction was regarded as being a marvel
of engineering in its day and was an extraordinary and outstanding accomplishment
for the time. The viaduct was 125 feet above the gully floor (equivalent to a 13
story building) and 341 feet long. The main uprights of the trestles and cross-spars
were 14 inches by 14 inches of solid kauri, each 40-foot long. A total of 212,000
superficial feet of well-seasoned kauri timber was used. Most of the timber was
milled up country and brought by sea into the Porirua harbour. Bullock teams then
dragged them to the site. A total of 35 tons of wrought iron bolts, nuts, washers
and fastening braces was used. The uprights stood on 14 concrete foundations in
the gully with some of the piers sunk 20 feet into the bed of the stream.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Photo: N.Z Railway & Locomotive Soc. Inc.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Photo: N.Z Railway & Locomotive Soc. Inc.
|
|
|
|
|
|
|
|
|
|
|
|
The Belmont Viaduct was described at the time
as looking like a gigantic web, or the puzzle of a dreaming geometrician.
The structure was designed by Mr. Harry P
Higginson using the experience he had gained in Russia and India. It was then built
by Mr. Morton Danaker, a Scandinavian specifically appointed for the construction.
The viaduct was built in sections on the ground
and the contractor achieved his greatest triumph by raising each structure section
by section, as they were ready, by using a block and tackle arrangement. It must
be remembered that this was more than 115 years ago.
|
|
|
|
|
|
|
|
|
In the early 1900's, the railway company decided
to reconstruct many of its original wooden bridges and consequently a prefabricated
steel bridge was erected around the old wooden structure, on the same centre line,
with rail traffic not delayed for even one hour. A travelling gantry arrangement
was erected over the track so trains could continue to pass underneath.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The travelling gantry crane
|
|
|
|
|
|
|
|
|
|
Photo: Alexander Turnbull Library
|
|
|
|
|
|
|
The four steel piers were built inside the
four existing pairs of timber trestles. When this was completed, the plate-girder
sections to carry the track were rolled out and dropped into place between the piers.
The old trestle could have lasted for many
years longer, but the threat of fire was of great concern to the company. The loss
of the viaduct would have had a devastating effect on their service because of the
time a replacement would have taken to construct.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
In 1908, the line was purchased by the government
and became part of the North Island Main Trunk Line. By 1937 it had reached the
limit of its capacity and the new double tracked Tawa Flat Deviation tunnel was
opened. As a matter of interest, the tunnel is positioned precisely under the old
viaduct beneath the valley floor at a depth of 24.5 metres (80 feet).
As a consequence of the opening of the deviation,
the old and steep hill route was permanently terminated at Johnsonville and the
viaduct abandoned after carrying steam trains for 52 years.
After rusting away for 14 years, it was agreed
in October 1951 that for public safety reasons, the complete viaduct would be removed
at the first suitable opportunity.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The new steel viaduct in 1903
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Photo: N.Z Railway & Locomotive Soc. Inc.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|

|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The viaduct partially demolished
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Photo: N.Z Railway & Locomotive Soc. Inc.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Arrangements were made with the Army to use
explosives in training exercises. The viaduct was 'blown up' by local territorial
Army engineers on 15 December 1951 after standing in place for 66 years, both in
wood and steel.
The removal of the Belmont Viaduct was the
passing of an era and gives Grenada Village a permanent mark of distinction.
The impression of the original height has
now been lost because of the nearby motorway embankment, the Mark Avenue filling,
and the fact that the tops of the surrounding hills have been levelled for housing.
However, when standing at the bottom of the gully today an idea of the viaducts
former size can be imagined.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Photo: National Archives of New Zealand
|
|
|
|
|
|
|
|
|
|
|
|