|
Grenada Village is the site of one of the great engineering achievements of 19th
century New Zealand. Seton Nossiter Park contains the remains of the famous Belmont
Viaduct that traversed the steep gully beside Mark Avenue. The viaduct was a memorable
and distinctive part of this country's early transport system.
|

The Belmont Viaduct
Photo: Alexander Turnbull Library
|
|
The original gigantic wooden span played an important role in developing early Wellington,
as not only did it open up the city's northern boundaries, it also provided access
to the 'hinterlands' of Horowhenua and Manawatu.
The viaduct was constructed for the privately owned Wellington & Manawatu Railway
Company in 1885 and was the largest wooden structure of its kind in New Zealand.
It was at the time reputed to also be the largest wooden viaduct in the world, however
this was later disproved as some spans in Canada were bigger.
|
|
Its construction was regarded as being a marvel of engineering in its day and was
an extraordinary and outstanding accomplishment for the time. The viaduct was 125
feet above the gully floor (equivalent to a 13 story building) and 341 feet long.
The main uprights of the trestles and cross-spars were 14 inches by 14 inches of
solid kauri, each 40-foot long. A total of 212,000 superficial feet of well-seasoned
kauri timber was used. Most of the timber was milled up country and brought by sea
into the Porirua harbour. Bullock teams then dragged them to the site. A total of
35 tons of wrought iron bolts, nuts, washers and fastening braces was used. The
uprights stood on 14 concrete foundations in the gully with some of the piers sunk
20 feet into the bed of the stream.
|
Photo: N.Z Railway & Locomotive Soc. Inc.
|
Photo: N.Z Railway & Locomotive Soc. Inc.
|
|
The Belmont Viaduct was described at the time as looking like a gigantic web, or
the puzzle of a dreaming geometrician.
The structure was designed by Mr. Harry P Higginson using the experience he had
gained in Russia and India. It was then built by Mr. Morton Danaker, a Scandinavian
specifically appointed for the construction.
The viaduct was built in sections on the ground and the contractor achieved his
greatest triumph by raising each structure section by section, as they were ready,
by using a block and tackle arrangement. It must be remembered that this was more
than 115 years ago.
|
|
In the early 1900's, the railway company decided to reconstruct many of its original
wooden bridges and consequently a prefabricated steel bridge was erected around
the old wooden structure, on the same centre line, with rail traffic not delayed
for even one hour. A travelling gantry arrangement was erected over the track so
trains could continue to pass underneath.
|

The travelling gantry crane
Photo: Alexander Turnbull Library
|
|
|
The four steel piers were built inside the four existing pairs of timber trestles.
When this was completed, the plate-girder sections to carry the track were rolled
out and dropped into place between the piers.
The old trestle could have lasted for many years longer, but the threat of fire
was of great concern to the company. The loss of the viaduct would have had a devastating
effect on their service because of the time a replacement would have taken to construct.
|
The new steel viaduct in 1903
Photo: N.Z Railway & Locomotive Soc. Inc.
|
In 1908, the line was purchased by the government and became part of the North Island
Main Trunk Line. By 1937 it had reached the limit of its capacity and the new double
tracked Tawa Flat Deviation tunnel was opened. As a matter of interest, the tunnel
is positioned precisely under the old viaduct beneath the valley floor at a depth
of 24.5 metres (80 feet).
As a consequence of the opening of the deviation, the old and steep hill route was
permanently terminated at Johnsonville and the viaduct abandoned after carrying
steam trains for 52 years.
After rusting away for 14 years, it was agreed in October 1951 that for public safety
reasons, the complete viaduct would be removed at the first suitable opportunity.
|
The viaduct partially demolished
Photo: N.Z Railway & Locomotive Soc. Inc.
|
Arrangements were made with the Army to use explosives in training exercises. The
viaduct was 'blown up' by local territorial Army engineers on 15 December 1951 after
standing in place for 66 years, both in wood and steel.
The removal of the Belmont Viaduct was the passing of an era and gives Grenada Village
a permanent mark of distinction.
The impression of the original height has now been lost because of the nearby motorway
embankment, the Mark Avenue filling, and the fact that the tops of the surrounding
hills have been levelled for housing. However, when standing at the bottom of the
gully today an idea of the viaducts former size can be imagined.
|
|
|
Photo: National Archives of New Zealand
|
|